Guidelines establishing project management standards and expectations for UMBC Enrollment Management. The document defines qualifying projects, outlines planning and approval requirements, and describes sponsor, lead, manager, team member and stakeholder roles. It covers project initiation, detailed planning, kickoff, execution, monitoring, assessment and completion, alongside expectations for staff training, professional development and performance feedback.
Free preview text
The first 5 pages, shown as text so search engines and readers can find this document.
Page 1
Project Management Guidelines & Best Practices
Project Management Philosophy
As UMBC continues to advance the goals and priorities outlined in the Strategic Plan for
Advancing Excellence and the Strategic Enrollment Plan, it will be imperative that we employ
best practices in project management that support effective and efficient planning and
development. Well-defined approaches to project management ensure that we are not only
good stewards of institutional resources but that we are able to be good partners as we
collaborate with others (both within and outside the UMBC community) on the planning,
development and execution of important initiatives. Further, clear and consistent project
management protocols help facilitate change management and promotes innovation. Finally,
project management is an essential workforce skill and demonstration of proficiency in and
experience with project management increases one’s marketability and opportunity for growth
and advancement.
The guidelines and protocols that follow detail the standards and expectations for project
management in Enrollment Management:
What is a Project?
A project is defined as a sequence of tasks that must be completed to attain a certain outcome.
Further, according to the Project Management Institute, the term Project refers to “any
temporary endeavor with a definite beginning and end”. Depending on its complexity, it can
involve a single person, entity or hundreds and include community members both within and
outside of the department. While we often think of technology-driven initiatives as projects,
projects can be non technical in nature. For example, event planning, school partnerships, and
student success initiatives are all considered projects in Enrollment Management.
Additionally, in Enrollment Management, a project includes one or more of the following:
● An institution-sanctioned initiative sponsored by a Dean, VP, Provost or President,
supporting the university mission (i.e. teaching, learning and research)
● An external system, state or federal mandate
● Engagement of other units within Enrollment Management, the University or a third party
● Requires the allocation of additional resources - personnel and/or financial beyond the
resources required for operational duties
Page 2
Project Planning Expectations and Standards
Successful projects require thoughtful planning. The following guidelines represent best
practices endorsed by the Project Management Institute (PMI)*, and adopted by Enrollment
Management, for facilitating projects from initiation through completion.
Steps for developing and executing project planning:
1. Establish the Project Charter
The project plan begins with a well-defined project charter. Establishing the project
charter will allow for the capture of specific project information and parameters that will
aid in project evaluation. Minimally, the charter should include a brief written description
and outline of the project that includes a clear statement about what problem are we
trying to solve or what opportunity we are pursuing, as well as the project scope,
stakeholders, timeline and budget and other resource requirements.
The project charter should be provided to the direct manager/supervisor and unit director
for review and consideration before initiating. After unit director-level review, the project
charter should be available to all project participants.
2. Initiation and Planning
Once a project charter is approved by the unit director, it formalizes the existence of the
project. Next step involves defining essential roles and responsibilities.
3. Define Roles and Responsibilities
All projects, minimally, should include the following roles:
Project Sponsor
Have a designated sponsor at the university leadership level (i.e. President,
Provost, Vice President, Vice Provost) that has committed the resources
necessary to support the project planning, execution and sustainability.
Ex: For the S/U Grade Option project, an academic policy initiative to better
support students experiencing academic difficulty in a course, Katharine Cole,
Vice Provost and Dean of Undergraduate of Academic Affairs, served as the
project sponsor.
Page 3
Project Lead(s)
A project lead is responsible for execution of the project plan. The project lead
may be responsible for specific aspects of a project or the entire project. They
may be responsible for developing the project plan, managing a small team,
general oversight of the project, and reporting on progress to the sponsor and
other higher-level management. In some cases, the project may warrant more
than one project lead (i.e functional lead, technical lead).
Ex: During the implementation of the Smart Panda Transcript Management
System, The Director of Admissions, serving as the project lead provides vendor
coordination, team goals regarding testing requirements, general project oversight
and provides reports on the project status to other EM and DoIT personnel.
Project Manager
A project manager is responsible for the day-to-day tactical execution of project
tasks and monitoring of the project efforts including regular updates of the status
of the project to the project lead. This role may be assumed by the project lead.
Ex: During the Articulation and School Partnerships on-going project, the
Associate Director for Transfer and Targeted Populations, and Partnerships,
serving as the project manager provides technical assistance to department
faculty to build out the articulation agreements. The Associate Director also
tracks, monitors and updates the status of the agreements.
Project Team Members
Individuals responsible for doing the work associated with a project will be
members of the project team. Each team member shall have a clearly articulated
and defined role. Roles should include, but are not limited to
● Recorder/Note taker
● Subject matter expert
● Business analyst
● Resource manager
● Quality assurance/Tester
● Technical support
Ex: For the Flexible Class/Term Scheduling project, which utilized a third party
consulting group and project management team, to expand our scheduling
options, the Associate Registrar for Systems served as one of the subject matter
experts.
Page 4
Project Stakeholders
Stakeholders are campus community members who will be affected by your
project at any point in its life cycle, and their input can directly impact the
outcome. Stakeholders can be within or outside Enrollment Management. Keep in
mind, students are one of our primary constituents and should be recognized as
an important stakeholder. Other stakeholders include faculty, staff, alumni, and
parents. Additionally, in accordance with UMBC values, it is important to include
different voices and perspectives (i.e. gender, race/ethnicity, social-economic) to
ensure the success of the project and that our work represents the diversity that is
UMBC.
Ex: For the Assign Advisor/Advisee project, which automates the assigning of
professional and faculty advisors to student advisees, stakeholders include
academic department advisors, undergraduate program directors and department
chairs.
4. Project Initiation Meeting(s)
An initial gathering of Executive Sponsor, Project Lead, and Project Manager to review
the project charter and broadly discuss the implications of the project.
5. Complete the Detailed Project Plan
The designated Project Sponsor, Project Lead and Project Manager will build out the
project plan, including detailed written description of estimated cost, scope, tasks and
timeline (milestones), and an assessment and evaluation plan. The detailed project plan
must be available prior to the start of the project.
6. Project Kickoff Meeting
The launch meeting is an opportunity to review the detailed project plan, roles and
expectations. Every effort should be made to include identified project members in the
initial launch meeting.
7. Execution, Monitoring and Control
Once the project commences, the project manager should monitor progress and update
the project status regularly, including:
• Tasks: Which tasks are completed and which are outstanding?
• Timeline: Have we achieved the desired milestones?
• Scope: Is the project still within the initially defined scope?
• Risks: Have any new risks been identified?
• Budget: What expenditures have occurred and are they within the established budget?
• Communication: Are you communicating with the project sponsor, team members and
stakeholders on a regular basis?
Page 5
8. Assessment and Evaluation
The health of the project requires a thoughtful and clearly defined assessment and
evaluation plan. The plan should include well-defined metrics. Metrics might include
quantitative measures, such as cost, time and resource utilization, as well qualitative
measures, such as user satisfaction. Project management assessment and evaluation
should drive continuous improvement during the project and post-project completion.
Additionally, major observations, findings and lessons learned should be reflected in the
overall EM Assessment Plan.
9. Project Completion
A project that has achieved the desired outcomes as articulated in the project charter,
shall be deemed complete. Completed projects must include:
• Business process documentation
• Lessons learned that will improve future projects
• Designated functional team member that will sustain the effort moving forward
• Must include project closeout report assessing overall project success and team
performance
Training, Development and Evaluation
Project Management is an interactive process. As such, investment in training, development
and evaluation is critical to continuous improvement and to ensuring a high standard of project
management practice across the organization.
Training and Development
Designated Project Managers and other key project team members shall be proficient in the
principles of effective project management as defined by the Project Management Institute.
Project Managers are expected to stay abreast of the ever-evolving standards of project
management. Training will be provided based on individual staff needs, which might include
online self-paced modules, conferences and workshops, or in-person classroom training.
Though not required, staff serving in PM roles are encouraged to seek full project management
certification. Staff are encouraged to work with their immediate supervisor to devise a training
and development plan.
Feedback and Evaluation
Project management is a learned skill that requires ongoing and continuous improvement; as
such, the project manager's should be provided an opportunity for regular routine feedback,
including what is going well, where there may be challenges and any resource needs.
Additionally, supervisors should utilize the annual Performance Management Process (PMP) to
acknowledge and document the PM’s role and contributions as well as areas for improvement.
Project Management Guidelines & Best Practices: summary, contents and background
This guide helps you understand the scope of Project Management Guidelines & Best Practices before or alongside reading the original document. It is based on the catalogue record, credited creator, source, classification and topics shown on this page. It does not replace the original work and does not invent claims about passages that Doxxly cannot verify.
Summary and overview
Project Management Guidelines & Best Practices is a 5-page documentcredited to Lior W. Oakfield. Guidelines establishing project management standards and expectations for UMBC Enrollment Management. The document defines qualifying projects, outlines planning and approval requirements, and describes sponsor, lead, manager, team member and stakeholder roles. It covers project initiation, detailed planning, kickoff, execution, monitoring, assessment and completion, alongside expectations for staff training, professional development and performance feedback. It appears in the Business & Economics collection, which groups it with other material that readers may use for comparison and further study.
The item can be approached in several ways. A reader looking for a quick orientation can begin with the free five-page preview, inspect the page structure and use the metadata to judge relevance. Someone undertaking deeper research can work through the complete file, search its indexed text, record useful page references and compare its treatment of Project management, Best practices, Enrollment Management, UMBC, Project planning, Roles and responsibilities, Stakeholder engagement, Assessment and evaluation, Professional development with the related resources linked below.
Rather than reducing the work to a single claim, this page treats it as a source that should be read in context. The title, creator, publication source, licence and format all help explain what kind of evidence it may offer. Readers should distinguish the original author's statements from Doxxly's catalogue description, and should cite the original edition when using the material in academic, professional or published work.
Key topics and reader takeaways
The catalogue connects this document with Project management, Best practices, Enrollment Management, UMBC, Project planning, Roles and responsibilities, Stakeholder engagement, Assessment and evaluation, Professional development. These terms offer practical entry points rather than a substitute for close reading. Start by identifying the definitions, examples, arguments, tables or visual explanations attached to each topic. Then note where the creator draws connections, makes distinctions or moves from background material to a conclusion, recommendation, calculation or narrative development.
A useful reading method is to separate description from interpretation. First record what the item actually presents: names, headings, figures, formulas, quotations or stated propositions. Next consider why those details matter within the whole work. Finally compare them with another source from the same subject area. This process helps turn a long digital file into evidence that can be evaluated rather than merely skimmed.
Table of contents and reading guide
The following is an editorial content guide based on the verified catalogue topics. It is not represented as the original author's formal table of contents. Use it to organise notes while moving through the 5 pages in the player.
Part 1
Project management
Use this section of the reading guide to identify how Project management appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
Part 2
Best practices
Use this section of the reading guide to identify how Best practices appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
Part 3
Enrollment Management
Use this section of the reading guide to identify how Enrollment Management appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
Part 4
UMBC
Use this section of the reading guide to identify how UMBC appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
Part 5
Project planning
Use this section of the reading guide to identify how Project planning appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
Part 6
Roles and responsibilities
Use this section of the reading guide to identify how Roles and responsibilities appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
Part 7
Stakeholder engagement
Use this section of the reading guide to identify how Stakeholder engagement appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
Part 8
Assessment and evaluation
Use this section of the reading guide to identify how Assessment and evaluation appears in Project Management Guidelines & Best Practices, note important terms, and connect the subject to the wider purpose of the work.
When a heading in the original differs from this guide, follow the original heading in your citation. Page numbers can also vary between editions. Doxxly's direct page field is useful for navigation, but formal references should include the title, creator, source and edition details available in the file itself.
About Lior W. Oakfield
Doxxly credits Lior W. Oakfield as the author or creator of Project Management Guidelines & Best Practices. This page does not add an unverified biography, job title or institutional affiliation. The attribution is preserved so readers can distinguish the creator from the hosting library and follow the original record when an external author link is available.
Author context matters because a work reflects a particular purpose, audience and point of view. Before relying on the material, consider what the creator set out to explain, when the source was produced and whether later research or revised guidance should also be consulted. For literature and philosophy, compare translations and editions; for technical material, check whether a newer version has superseded the one shown here.
About the source organisation
The recorded source for this item is emservices.umbc.edu. Doxxly provides access and discovery tools but does not claim to be the original publisher unless explicitly stated. Source links, creator attribution and the recorded Publicly available file collected for editorial review licence are displayed to help readers assess provenance and permitted use.
Provenance is especially important for reports, standards, presentations and working spreadsheets. Check the original source for amendments, supporting files and current policy. A trustworthy research workflow keeps the source URL with any notes or downloaded copy, verifies important figures against the original, and avoids treating an archived document as automatically current.
Begin with the title and opening pages, then use the guide above to decide whether to read sequentially or move to a particular topic. The Doxxly player provides previous and next navigation, a direct page field, zoom steps, fit-to-width and fit-to-page modes, rotation and fullscreen. These controls are useful when a page contains small type, a wide table, an image, a scanned layout or a dense sequence of notes.
The first five pages are open to every visitor. A plan unlocks the complete item and full-document search. Search is best used for distinctive names, technical terms or short phrases; broad words can produce too many possible contexts. When you find a useful passage, read the surrounding pages so that a sentence, chart or formula is not separated from its explanation.
If downloading is enabled, members can obtain the original PDF file. Keep the original format when formulas, slide sequencing, pagination or layout carries meaning. Respect the Publicly available file collected for editorial review terms displayed on this page, and use the rights-report link if you believe the attribution or availability needs review.
Research questions to consider
As you read Project Management Guidelines & Best Practices, ask which audience the creator addresses, what problem or idea organises the work, what evidence is presented, and which assumptions remain unstated. Note whether important terms are defined consistently and whether examples represent a broader pattern or a narrow case. For quantitative material, record units, time periods, formulas and data sources. For interpretive material, separate the creator's language from your own summary.
A second set of questions concerns relevance today. Which parts remain durable, which depend on their historical or institutional setting, and what would need confirmation from a newer source? Following the tags and the Business & Economics collection can reveal useful comparisons. Agreement between sources can strengthen confidence, while disagreement can point to changing definitions, methods, evidence or priorities.
Finally, decide what you need from the item: background knowledge, a quotation, a worked example, a model, a visual explanation or a starting bibliography. That purpose should guide the depth of reading and the notes you keep. Doxxly helps locate and navigate the source; careful interpretation remains the reader's responsibility.